On September 23, 2025, Hendersonville's Board of Mayor and Aldermen voted 13 to 0 against annexing 32.8 acres at 1765 Avant Lane, south of Old Drakes Creek Road. The plan was a subdivision called Crestwater. On September 8, 2026, almost a year later, the same board voted unanimously, with one alderman absent, to approve the plan of services and first-reading rezoning for the same acreage. The new plan is called Avelyn.
The land stayed the same, and so did the board. What changed was who would pay for the streets and the garbage trucks once the homes were sold.
For anyone shopping new construction in Hendersonville, that shift explains a lot. The city's own numbers show that fewer, higher-value homes on private streets maintained by a homeowners' association make sense for the city budget, while denser plans relying on city services do not. In a subdivision built this way, the HOA covers costs the city carries in older neighborhoods, and buyers pay for that through their dues.
The fiscal math the mayor read into the record
At the September 2026 meeting, Mayor Jamie Clary walked the board through a staff comparison of four scenarios. Here are the three that apply to the Avant Lane parcel, as recorded in the September 8, 2026 meeting minutes.
| Scenario for 1765 Avant Lane | Estimated annual effect on the city |
|---|---|
| Leave it in the county under current zoning | About $21,000 benefit |
| Crestwater proposal | About $19,000 cost |
| Avelyn, 36 homes | About $37,000 benefit, plus about $216,000 in impact fees at $6,000 per home |
The staff comparison also included a fourth scenario, Oak Creek, which the minutes mention only as a point of comparison.
The mayor attributed Avelyn's better numbers mainly to two features. The homes would be higher in value, and the streets and infrastructure would be private and maintained by the homeowners' association rather than the city. He estimated about $2,400 in annual city revenue per property against about $1,950 in annual city expenses. He added that even if projected sales-tax revenue came in at half the estimate, the development would still return about $14,000 a year.
Garbage followed the same logic. Planning Director Keith Free told the board the standard refuse-collection language in the plan of services did not need to come out, because staff could set it in the development plan that the homeowners' association would handle garbage and limb collection.
In that arrangement, the city collects property tax from each home while the HOA, funded by owners' dues, covers road upkeep and trash pickup. A buyer's monthly cost in Avelyn will include services that a buyer a few miles away in an older neighborhood with city streets receives through taxes alone.
The board asked for this structure a year earlier
The 2026 approval followed a request the board made out loud in 2025.
During the Crestwater debate, Alderman Collins said she would vote no. She suggested that residents ask for an HOA whose bylaws include trash, yard waste and limb removal, and for the architectural standards of neighboring Durham Farms to be adopted at the site plan stage. Other aldermen pressed Century Communities, the developer, on whether it could cut the home count sharply and build homes similar to those in Durham Farms. The company's representative said the plan could go below 61 homes and floated a possible cap of 40, but said cutting the count in half would not support the extra amenities on offer.
Public comments that night described Crestwater as a 61-home plan. The 2026 minutes recorded a speaker referring to the earlier plan as a 65-home proposal. The plan that came back was 36 homes, and residents who spoke at the September 8, 2026 meeting described it as a gated community with streets maintained by the homeowners' association, different from the prior proposal. A home count more than a third lower, HOA-run services and a gate are close to what the board and residents described in 2025.
Why the city annexes at all
Annexation is the city's main source of leverage. In 2025 the developer's representative noted that the parcel is zoned for one unit per acre in the county, and that a county plan could hold anywhere from 30 to 40 homes using cluster or planned-unit options. Alderman Garza warned that if the city declined to annex, the development could still happen under the county, and "the City would have no control over it."
At 36 homes on 32.8 acres, Avelyn comes to roughly 1.1 homes per acre, close to what the county zoning would allow. The city did not gain extra homes by annexing. It gained the right to set the terms: architecture, HOA responsibilities, a plan of services, and $6,000 in impact fees per home.
Planning Director Free also explained how a rejection works. A developer whose plan fails has to wait a year before returning unless the new plan is substantially different, in which case it can go back through the Planning Commission sooner. A buyer looking at a newly approved Hendersonville subdivision may be looking at a second or revised version of a plan, shaped by what the board turned down the first time.
A density debate that wasn't about high density
It would be easy to connect the Avant Lane outcome to Hendersonville's moratorium, but the moratorium covered a different kind of project. On August 26, 2025, the board passed Ordinance 2025-14 by a 10 to 2 vote. It imposed a nine-month moratorium on accepting, reviewing or approving applications and permits for high-density residential development. Main Street Media reported that the threshold was more than eight units per acre. In an April 30, 2026 article, it said the moratorium was expected to expire May 26 and that aldermen were discussing an extension. The records gathered for this post do not confirm whether an extension was adopted.
Crestwater, at roughly 61 homes on 32.8 acres, worked out to under two homes per acre. That is far below the moratorium threshold, and it still failed 13 to 0. In Hendersonville, objections to density start well below what most people would call high density. Residents at the 2025 hearing raised traffic, stormwater and infrastructure, and asked that roads catch up before more homes are added.
Infrastructure has funding but no construction dates
Those infrastructure concerns now have funding behind them, but not yet a construction schedule. In July 2026 the city announced federal transportation grants for six projects estimated at $93.5 million in total. The city expects grants to cover about 80 percent, or roughly $75 million, and the first award is anticipated to be $11 million, mostly for pre-construction work. The six projects are:
- Center Point Improvements, with widening and curve corrections between Mansker Farms Boulevard and Hunts Lane
- Widening and safety work on Indian Lake Road
- A one-mile West Main Street access-management and reconstruction project
- Intersection work at Sanders Ferry Road and Imperial Boulevard
- Innsbrooke and Saundersville Intersection Improvements, with widening and circulation work around the Innsbrooke Avenue and Dayflower Drive intersections
- A roundabout at Rockland Road and Imperial Boulevard
The announcement gave no construction schedules. Funding for the construction phase depends on design, engineering and right-of-way acquisition getting close to completion. That timing helps explain the board's interest in developments that pay for their own roads, since the city's road projects are still at the design stage.
What the price doesn't show
Regional prices are still rising. Greater Nashville REALTORS reported a September 2026 residential median of $510,000 across its nine-county region, up from $490,000 a year earlier. The region had 5.7 months of inventory, and single-family homes averaged 57 days from listing to contract. Active listings were up 6 percent year over year, so buyers have more homes to compare than they did a year ago. In Sumner County, the Q3 2026 quarterly report shows a residential median of $475,000 on 906 sales and a condo median of $324,315 on 105 sales.
A median price compares homes as though owning each one costs the same to run, and in Hendersonville that is less true than it used to be. A home in a private-street, HOA-serviced subdivision and a home on a city street with city garbage pickup can list at similar prices and carry different monthly costs. The first owner pays the city's property tax plus dues that fund road upkeep and trash pickup. The second gets those services through the tax bill.
In a transaction, the gap usually shows up when the HOA documents arrive. The documents that set these responsibilities are public. Each annexation comes with a plan of services passed by resolution, and the development plan and HOA bylaws spell out what the association handles. For Avelyn, the minutes describe garbage and limb collection as an HOA responsibility to be written into the development plan.
Avelyn and the zoning rewrite are both still pending
The Avelyn rezoning, Ordinance 2026-09, has passed first reading only. At the September meeting, staff said stormwater comments were still under review and that the developer was working through the outstanding issues. The same night, the board passed the first reading of Ordinance 2026-10, a citywide revision of the zoning ordinance. According to minutes of the August 11, 2026 General Committee meeting, it had been through two Planning Commission meetings and two public hearings, and the planning director described it as affecting what, where and how the city builds. Before second reading, Alderman Martin asked staff to consider raising the proposed setback for data centers from residential districts from 100 feet to 500 feet, and to look further at noise standards.
Questions buyers ask about this
Does every new Hendersonville subdivision have private streets? No. The fiscal analysis described here comes from the Avelyn record. It shows why the board favored that design for this parcel, but it does not set a citywide rule.
Where can I see what the HOA will handle versus the city? The plan of services adopted by resolution and the development plan are public records on the city's agenda center. The HOA bylaws spell out the association's duties.
Is the high-density moratorium still in effect? It was set to expire May 26, 2026, and an extension was under discussion in late April. The sources reviewed here do not confirm what happened after that.
When will the road projects be built? The city's July 2026 announcement gave no construction schedules. The first award is anticipated to be $11 million, mostly for pre-construction work.